Production Update - May 14, 2018

Posted by Brad Hellyar on

Today we met with the manufacture to finalize the changes that need to be made for the mold to be 100%. He was confident that by the end of day the mold would have all the discussed changes made and we would be able to see new samples by the end of the week, May 18, 2018.
Read more →

Production Update - Tooling is Done but not Finished!

Posted by Brad Hellyar on

The manufacturer has produced 10 units for quality, fit, and functional testing. This is to say the mold (the injection mold or tooling) is done but will undergo the necessary tweaks that will be discovered before it is finished and ready to do a first production run.
Read more →

The Mag Feeder is in the Tooling Phase!

Posted by Brad Hellyar on

I got a call on my drive to work from the manufacturer with great news! He proceeded to inform me that they are beginning the tooling for the mold on The Mag Feeder. I was so excited I could have crashed and died and it wouldn't have ruined my day (ok maybe just a little)! 
Read more →

KEEPING IT STATE SIDE

Posted by Brad Hellyar on

The Preorder sale of The Mag Feeder will extend the duration of the time the tooling takes to be made in America. Yes, I could have gone to China or Mexico at this point and completed the tooling and started manufacturing The Mag Feeder, but I feel like if every company sells out then who is left to keep America turning. Not saying that my one little act to hold out for American tooling will forever save the American economy but if more companies used this logic it would make a difference.
Read more →

Timeline - Update

Posted by Brad Hellyar on

So, Tooling times have slipped....currently looking for a new American based manufacturer so I can meed the attached timeline. Not too concerned as the few I spoke with today had a 4-5 week build time so I have some cushion room. 
Read more →